Simevents: Changing resources in pool

4 ビュー (過去 30 日間)
Mats
Mats 2021 年 1 月 14 日
回答済み: Abdolkarim Mohammadi 2021 年 2 月 5 日
Hi,
I am trying to change the amount of resources in a resource pool between a day shift and a night shift (different number of forklifts).
I have created a system which sends a signal of four during the day hours and two during the night but this gets added when the message is sent to the resource pool (added all the time so I end up with well over 200 forklifts).
What is the correct way to vary resources in a pool since the input value cannot be negative (so cannot withdraw resources).

回答 (1 件)

Abdolkarim Mohammadi
Abdolkarim Mohammadi 2021 年 2 月 5 日
One way is to create a Gate, and not to let entities when the resource is not sufficient. The other way, which is the better but harder way, is to use MATLAB Discrete-Event System (MDES) block.

カテゴリ

Help Center および File ExchangeDiscrete-Event Simulation についてさらに検索

製品


リリース

R2019b

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by