Hello,
I have a cell containing two cell columns. Column 1 is date and Column 2 is hour. I want to merge them together and transfrom date/time to the Matlab format. I am using a 'for' loop to do this, because I wasn't able to do it using 'cellfun'. This is the code:
for i=1:385521
PT{1}{i,1} = datenum(strcat(PT{1,1}{i,1},PT{1,2}{i,1}),'dd.mm.yyyyHH');
end
This works, but it takes about 6 minuts to do this operation. Could you give me some suggestions on how to optimize this operation. Even better if it is not in a loop.
Thanks, DjR
  1 件のコメント
djr
djr 2015 年 2 月 10 日
This is the sample of the input file (first few lines) and the whole for loop:
fid = fopen('test.txt');
PT = textscan(fid, '%s %s %f %f','Delimiter',',', 'HeaderLines',1);
fclose(fid);
clear ans fid
% Organize data (remove 00:00:00) and convert date to Matlab format
PT{1} = cellfun(@(x) strrep(x, ' 00:00:00',''), PT{1},'UniformOutput',false);
PerRow = cell2mat(strfind(PT{:,1},'.'));
for i=1:length(PT{:,1})
% add two zeros if format is m.d.yyyy
if PerRow(i,1) == 2 && PerRow(i,2) == 4
PT{1}{i,1} = ['0', PT{1,1}{i,1}(1:2), '0', PT{1}{i,1}(3:end)];
% Add one zero if format is d.mm.yyyy
elseif PerRow(i,1) == 2 && PerRow(i,2) ~=4
PT{1}{i,1} = ['0', PT{1}{i,1}];
% Add one zero if format is dd.m.yyyy
elseif PerRow(i,2) == 5
PT{1}{i,1} = [PT{1}{i,1}(1:3), '0', PT{1}{i,1}(4:end)];
end
% Add zero if format is H
if size(PT{1,2}{i},2) == 1
PT{1,2}{i}=['0', PT{1,2}{i}];
end
% Combain columns and transform date/time to Matlab format
PT{1}{i,1} = datenum(strcat(PT{1,1}{i,1},PT{1,2}{i,1}),'dd.mm.yyyyHH');
end
clear i PerRow
The loop without the problematic line takes only about 20 sec on my Linux computer.

サインインしてコメントする。

採用された回答

Titus Edelhofer
Titus Edelhofer 2015 年 2 月 10 日
Hi,
you should do the strcat out of the loop, something like
PT12 = strcat(PT{1,1}(:,1), PT{1,2}(:,1));
and then you don't need the loop on datenum
PTnum = datenum(PT12, 'dd.mm.yyyyHH');
Titus
  3 件のコメント
djr
djr 2015 年 2 月 10 日
Thanks a lot. It is much more efficient. It takes like 30 seconds to finish. It took about 6 minutes when the line was in the loop.
Titus Edelhofer
Titus Edelhofer 2015 年 2 月 10 日
Your welcome. Usually MATLAB is not that bad on loops anymore. But datenum is using a MEX file in the back ground, which has some overhead when called in a (large) loop.

サインインしてコメントする。

その他の回答 (0 件)

カテゴリ

Help Center および File ExchangeDates and Time についてさらに検索

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by