can this loop be optimized? It is called 1m times and is the only thing I couldn't optimize yet.
Oper_year=1:1:Lifetime;
[costM,PVcost,YearProd,Elcost]=deal(zeros(size(Oper_year)));
for j=1:1:length(Oper_year)
if j==1
costM(j)=Mcost*PVprice*PVP;
PVcost(j)=PVprice*PVP+Bcost;
YearProd(j)=sum(PMDb)*PVP;
Elcost(j)=Elprice;
Bcost(j)=Bcost;
else
Bcost(j)=Bcost(1)*(1+bank*Oper_year(j-1));
costM(j)=PVprice*(Mcost*(1+Minf)*(Oper_year(j-1))+Mcost)*PVP;
PVcost(j)=(PVprice*PVP)*(1+bank*Oper_year(j-1))+Bcost(j);
YearProd(j)=sum(PMDb)*PVP*((1-PVdeg)*Oper_year(j-1)+1);
end
end
thanks

採用された回答

KSSV
KSSV 2020 年 2 月 8 日
Oper_year=1:1:Lifetime;
[costM,PVcost,YearProd,Elcost]=deal(zeros(size(Oper_year)));
costM(1)=Mcost*PVprice*PVP;
PVcost(1)=PVprice*PVP+Bcost;
YearProd(1)=sum(PMDb)*PVP;
Elcost(1)=Elprice;
Bcost(1)=Bcost;
Bcost(2:end)=Bcost(1)*(1+bank*Oper_year(1:end-1));
costM(2:end)=PVprice*(Mcost*(1+Minf)*(Oper_year(1:end-1))+Mcost)*PVP;
PVcost(2:end)=(PVprice*PVP)*(1+bank*Oper_year(1:end-1))+Bcost(2:end);
YearProd(2:end)=sum(PMDb)*PVP*((1-PVdeg)*Oper_year(1:end-1)+1);
  5 件のコメント
KSSV
KSSV 2020 年 2 月 8 日
The error is becasue the variable Bcost has been treated as scalar as well as vector. Rename the scalar Bcost to some other name. I followed like below:
% some random values for demo
Lifetime = 12 ;
Mcost = rand ;
PVprice = rand ;
PVP = rand ;
BCost = rand ;
PMDb = rand ;
Elprice = rand ;
bank = rand ;
Minf = rand ;
PVdeg = rand ;
Oper_year=1:1:Lifetime;
[costM,PVcost,YearProd,Elcost,Bcost]=deal(zeros(size(Oper_year)));
costM(1)=Mcost*PVprice*PVP;
PVcost(1)=PVprice*PVP+BCost;
YearProd(1)=sum(PMDb)*PVP;
Elcost(1)=Elprice;
Bcost(1)=BCost;
Bcost(2:end)=Bcost(1)*(1+bank*Oper_year(1:end-1));
costM(2:end)=PVprice*(Mcost*(1+Minf)*(Oper_year(1:end-1))+Mcost)*PVP;
PVcost(2:end)=(PVprice*PVP)*(1+bank*Oper_year(1:end-1))+Bcost(2:end);
YearProd(2:end)=sum(PMDb)*PVP*((1-PVdeg)*Oper_year(1:end-1)+1);
Asliddin Komilov
Asliddin Komilov 2020 年 2 月 8 日
I got the point, I will see if it will be faster than the existing code. Thanks

サインインしてコメントする。

その他の回答 (0 件)

カテゴリ

Help Center および File ExchangeLogical についてさらに検索

製品

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by