I am using the app designer to create a UI with a graph (app.Graph), a hold switch (app.HoldGraphSwitch) and a calculate button (app.CalculateButton).
I want it so when the hold switch is set to 'on', then the graph holds the previous plots on the graph but if set to 'off, then the graph clears previous plots.
I have tried the following but does not clear the graph:
function CalculateButtonPushed(app, event)
if app.HoldGraphSwitch.Value==0
hold(app.Graph, 'off')
else
hold(app.Graph, 'on')
end
plot(app.Graph,x,y)
end
Any solutions would be appriciated :) Thanks!

採用された回答

Cris LaPierre
Cris LaPierre 2018 年 11 月 9 日
The hold command only tells it how to treat the next plot. Clearing your axes is a different process. There are numerous ways to do it, so it depends what functionality you want.
Consider using cla(app.UIAxes). You can read more about cla here .
Other options include clearing the line object's XData , YData, ... properties.
  1 件のコメント
Donny Wong
Donny Wong 2018 年 11 月 10 日
Thank you, that seems to have done the trick.

サインインしてコメントする。

その他の回答 (0 件)

カテゴリ

Help Center および File Exchange2-D and 3-D Plots についてさらに検索

タグ

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by