my objective is to minimize the settling time....so at each and every time have to calculate settling time...for that am using stepinfo syntax
result is coming like below
S = RiseTime: 0.0015
SettlingTime: 17.4555
SettlingMin: 48.2799
SettlingMax: 50.7285
Overshoot: 1.4607
Undershoot: 0
Peak: 50.7285_
PeakTime: 5.9900
so how can i take settlingTime or any value to another variable
am grateful to u if u respond _____________THANKING YOU
  1 件のコメント
POLURI SRIMANNARAYANA
POLURI SRIMANNARAYANA 2017 年 12 月 1 日
but i'm not using any transfer function model...frequency is an array from iterative procedure i have an array..

サインインしてコメントする。

採用された回答

Birdman
Birdman 2017 年 12 月 1 日
Consider this approach:
Gs=tf(1,[1 1]);
result=stepinfo(Gs);
SettlingTime=result.SettlingTime
  3 件のコメント
POLURI SRIMANNARAYANA
POLURI SRIMANNARAYANA 2017 年 12 月 1 日
yes yes got it
THANKYOU SO MUCH sir
Birdman
Birdman 2017 年 12 月 1 日
Ok then. If S you wrote is a struct, then just write
S.SettlingTime

サインインしてコメントする。

その他の回答 (0 件)

カテゴリ

Help Center および File ExchangeMatrix Indexing についてさらに検索

タグ

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by